Hello All. A quick update for the last weeks progress: *The large upper water storage tank re-inforcement steel was placed exterior waterproofing finished and the 7" thick concrete slab was poured (the tanks top) Only interior detailing remains.
*Work began on the storage bodega/ramp and retention walls which connects the tank to ground level below *The upper pool SW corner, detailing has been completed (only tiling remains) and work has begun on a retention wall from it eastward to support the patio and rancho. *Progress continues on the sewage install in the SW corner *The area for the large infinity pool and parking lot has been filled/compacted and thus prepared for work to begin on the waterfall and then the pool. *The two central parking areas had concrete tubings placed and fill/compaction was performed to make room for the approx 40 spaces alloted there. *The centermost small pool was dug, re-inforcement steel placed and floor poured. This pool will also contain some waterfall effects. *The NE corner large pool detailing continued and is almost finished, A hydromassage seating area has been added to the plans and work began yesterday on it. *AYA water inlet tank exterior sealing and interior details were finished, An interior seal coat remains along with its electrical support closet/bodega. *The main road was lowered almost 2 meters in one area with large rocks excavated, this explains why it was not down to an acceptable grade to begin with as the previous contractor most likely felt it was not cost effective to remove these rocks. We have use for them and it would have cost more to buy them than excavate. Thank you for you continued patience in this matter as we have another 100 meters of distance to cover, lowering aprox. 1 meter in some areas, this will make a mess and with rains, a muddy mess but it must be done to provide proper drainage and yard/entrance/curb appeal to some of the units. Overall, progress continues at predicted pace. We are ahead of schedule and on budget. Scott Hansen
|