Current status of the Las Torres del Coco project
Dear Coco Tores owners,
I am sure that this email will surprise a lot of you and some of you are aware of the current status with the Coco Tores project.
Let me first introduce myself, my name is Sorin Costache and together with Anatoli Barsukov we represent the buyers of 24 units in Coco Tores project out of which 3 of them we own.
Many of you have heard and seen the current status of this project, but let me give you a quick update:
1. All the units are finish and they are ready to be furnished whenever each owner decides to.
2. There is a tank of 1000 liters that provides water for the project which is for now temporally, I am sure that you all are aware of the water meters now required by the "coco water project" to be installed at each unit in order to eliminate the blue tank that is now sitting at the side of one of the buildings.
3. Some of the common areas such as (the back parking lot, the wall between Mapache's office and the project...) are still not finished. There is little, or better no effort put in by Grupo Mapache to finish these items that have been pending for some time.
4. The project is now clear of loans and is at no risk of being foreclosed like other Mapache projects that are now in the process of negotiations with various lenders in order for some of these projects to be saved. Luckily Coco Torres does not face this problem, but we encounter the following:
5. The electrical issue is still not resolved due to a change in requirements by the electrical company "Coope Guanacaste". They now require two transformers of higher capacity in order to service the whole project with enough electricity.
We keep on asking ourselves when can we enjoy our investments and when we can rent these units so we can all see some returns from this investment financed by hard eared money or equities that have now depleted due to the economical downturn.
The answer is: not unless these units are completely finished with electrical installation, and finishing of the rest of the pending work.
So, "who is going to do all this work"? - of course is Grupo Mapache's responsibility, that is what they promised when we bought these units and that is what a developer must do, finish the work. Sounds nice and simple if Grupo Mapache would have the funds to finish this project, but I think by now is no mystery that they are in enormous financial distress, and unable to deliver their contractual obligations.
In the last visit that my partner Anatoli made in the beginning of February; during many meetings with Carlos Arroyo the owner of Grupo Mapache EIG he learned the whole story about these transformers and how we can get this done. Of course we are open to many ideas but this is what we proposed.
1. We thought it was important to understand the whole job and evaluate the cost.
2. We understand that at this point these is only one company qualified and competent that can and will guarantee the job done as per "Coope Guanacaste" requirements. That is to build the concrete basis, wire the whole project, install electrical meters and transformers.
3. Begin to inform the buyers of the situation and start raising money to complete the project.
Here is a list of funds necessary:
$40.000.00 USD to install transformers
$12.000.00 USD To build the concrete boxes for the transformers, to finish all the parking areas, $ 5.425.00 USD
Landscaping for the whole property. (second quote pending)
$57.425.00 TOTAL
The owner from unit number 24 did not pay for his final balance, so there is $3950.00 to collect plus the additional cost of the work necessary.
The lawyer has in the "TORES del COCO" trust account the sum of $5500.00
$57425.00 -
5500.00
3950.00
$47975.00 this divided by 48 units is $1000.00 per unit
We plan on being there in the end or mid March to start the work and be there until finish.
We will provide full accountancy and receipts to all owners of the project and maintain everything transparent and for everyone review.
You will need to deposit these funds in "TORES del COCO" trust account opened by
”Bufete José Manuel Arias González & Asociados S.A."
Please make your recommendations as quick as possible so we can have a solid plan by the end of this month and then begin collecting the funds for the necessary work.
We must also plan ahead and get proposals from couple of Management Companies, we will do that during our trip.
UNDERSTAND THAT UNLESS WE HAVE everyone's cooperation WILL BE VERY HARD TO GET THIS DONE, SO PLEASE RESPOND IN A TIMELY MANNER.
Thank you,
Sorin Costache