Week # 52 Tree Top Terrace Condominiums February 7, 2010
The following jobs were completed:
1- We are working on the walls of the condo number 17; also we are doing the special beams
to support the roof structure of that condo. We fill with concrete the columns of this condo, in
order to finish the concrete walls. We are doing a great advance in this condominium.
2- We are working on the steel roof structure of the condo number 17; we are going to start
doing the principal steel truss.
3-We are filling with concrete the interior columns of the condo number 10.
3-We keep working on the collocation of the tiles of the condo model, we are working on the
master bedroom and both bathrooms. It is looking great; the tiles colors match each other’s
perfectly.
4- We are doing the steel beams of the concrete floor slab of the exterior terraces of the condo
number 17, we hope finish that terrace next week hopefully.
5-We do three circular concrete columns that support the third level condos.
Attached photos showing the advance.